ASIL Merone S.p.A.
Consortium installations
With the entry into force of Lombardy Regional Regulation No. 3 of 24 March 2006, the plant required an upgrade of its purification capacity.
Design flow rate = 1,200 m3/h in dry weather – 4,400 m3/h in wet weather
Capacity = 120,000 A.E.
Process designer
Civil, electro-instrumental, piping designer
Geologist, agronomist
Design: 2006 – 2013
Completion of construction and start of testing: end of 2017
6.500.000,00 €
Pre-feasibility, preliminary and final.
Adaptation of the Merone (Como) purification plant to the new emission limits established by Lombardy Regional Regulation no. 3 of 24 March 2006.