Industrial waste and liquid waste treatment plant

Client

Industrial waste and liquid waste treatment plant

Application

Wastewater treatment plant industrial effluents and liquid waste

Purpose of the project

Conceptual study: analysis of possible water cooling systems for the sludge drying plant.

Team

Project manager

Process Engineer Expert

Timing

March-September 2024

Performed services

  • Plant audit
  • Project Bases
  • Technical-economic conceptual study

Activities

  • Review of available documentation
  • On-site meeting for verification with the client
  • Definition of the technical basis of the study
  • Identification of available areas
  • Analysis of possible applicable plant technologies
  • Conceptual technical-economic study of applicable plant solutions

Project Plus

  • Ability to interface with the client to better understand the production process, the criticalities present and the needs required
  • Actual indication of possible management-plant alternatives with evaluation of the strengths/weaknesses of each solution